Improvements Progressing On Newport Cycle Track

CYCLEWight
Published by in Campaigning ·
Work to create an upgraded shared use route between The Riverside Centre and Mews Lane in Newport is progressing well.
The scheme is part of the Isle of Wight Council’s ongoing work to encourage greater use of cycling and walking by creating high quality shared-use paths.
Transport grants
The project is being carried out by Island Roads using money the council has been awarded through the government’s Active Travel 2 and Local Transport Plan programmes.
The first phase of the work between Mews Lane and Halberry Lane — which is the longest phase both in terms of length of footpath upgraded and duration — is complete and phase two (Halberry Lane to Gordon Road) is on track to finish at the end of November.
Third section to begin
As work on the second phase draws to an end, work will begin on the third section — between Gordon Road and the junction of St Paul’s View/Victoria Road — on Monday 29th November. This means that for a short time, there will be work on both phases two and three.
On completion of the third phase in late December, the scheme will take a pause in order to tie in work on the final phase — St Paul’s View/Victoria Road to The Riverside Centre — with the scheme to upgrade the traffic lights and pedestrian crossings at Coppins Bridge and its approaches.
Last phase in Feb 22
Therefore, coinciding with the Coppins Bridge work on the Fairlee Link Road, the last phase will commence on Monday 21st February 2022 with a planned completion date of Friday 11th March.
This will mean that the temporary pedestrian crossing facilities at the junctions of Fairlee Road and Hillside, and Link Road and Fairlee Road, will be the only traffic control in this vicinity during work.